Hi abstr,
I removed that choose and the otherwise condition and it all works as expected now.
Thank you.
Search found 41 matches
- Tue Apr 08, 2025 9:03 am
- Forum: Stylesheets (XSLT)
- Topic: z_DetailedReport refers to a non-exitent attribute
- Replies: 2
- Views: 2809
- Thu Apr 03, 2025 12:59 pm
- Forum: Stylesheets (XSLT)
- Topic: z_DetailedReport refers to a non-exitent attribute
- Replies: 2
- Views: 2809
z_DetailedReport refers to a non-exitent attribute
Hi All, I was playing around with the Z_DetailedReport transformation and ran into an issue that turned-out to be a test containing REFID. (line 613) So I was wondering what that attribute is used for, and can I safely ignore it? I see that it is in the TDL file, but not supplied to the transformati...
- Thu Oct 24, 2024 11:38 am
- Forum: Suggestions
- Topic: Hide Group By dropdown
- Replies: 0
- Views: 151
Hide Group By dropdown
Hi,
I don't use and have never used the "Group by" dropdown above the tasklist. It uses-up valuable screen real-estate on smaller screens.
Would it be possible to add a Preference to hide "Group by" and the Options dropdowns?
Craig
I don't use and have never used the "Group by" dropdown above the tasklist. It uses-up valuable screen real-estate on smaller screens.
Would it be possible to add a Preference to hide "Group by" and the Options dropdowns?
Craig
- Wed May 31, 2023 7:37 am
- Forum: 8.2 Stable Release
- Topic: Week Planner - Task Height
- Replies: 8
- Views: 1785
Re: Week Planner - Task Height
Cool,
It had to be something stupid like an incorrect working-day setting. Otherwise everybody would have been complaining.
Thank-you for taking a look.
It had to be something stupid like an incorrect working-day setting. Otherwise everybody would have been complaining.
Thank-you for taking a look.
- Tue May 30, 2023 8:25 am
- Forum: 8.2 Stable Release
- Topic: Week Planner - Task Height
- Replies: 8
- Views: 1785
Re: Week Planner - Task Height
Attached. The first task "This is a Task" has been changed to have a start and due date of today and a Time Estimate of 1 hour. View it in the week planner and the issue becomes apparent. Drag the end-time up to 1 hour and the Time estimate is zeroed. Set the time estimate back to 1 hour and the Due...
- Sun May 28, 2023 6:55 pm
- Forum: 8.2 Stable Release
- Topic: Week Planner - Task Height
- Replies: 8
- Views: 1785
Re: Week Planner - Task Height
Already selected. Image04.png The time estimate definitely does change when the Due Time is changed, but the calc seems off. When I set the time estimate to 1H, the due Time is moved 6 hours ahead. when I set the estimate to 2H, the due time is set 7 hours ahead - 3h is 8H ahead etc. There's always ...
- Fri May 26, 2023 7:46 am
- Forum: 8.2 Stable Release
- Topic: Week Planner - Task Height
- Replies: 8
- Views: 1785
Re: Week Planner - Task Height
The due time matches the block height in the Weekly Planner.
It's only the Time Estimate calculation that seems out of line. It's quite possible that I don't fully understand how this works, I assume that the Gantt chart will also be affected by this.
It's only the Time Estimate calculation that seems out of line. It's quite possible that I don't fully understand how this works, I assume that the Gantt chart will also be affected by this.
- Thu May 25, 2023 11:44 am
- Forum: 8.2 Stable Release
- Topic: Week Planner - Task Height
- Replies: 8
- Views: 1785
Week Planner - Task Height
Hi,
I see that a 30 minute task shows in the Week Planner as 3h30 high. If I use the mouse to drag the task block down to 30 minutes, then the Time Estimate is reduced to zero.
I see that a 30 minute task shows in the Week Planner as 3h30 high. If I use the mouse to drag the task block down to 30 minutes, then the Time Estimate is reduced to zero.
- Fri Mar 17, 2023 7:46 am
- Forum: 8.2 Stable Release
- Topic: Certain Keyboard Shortcuts - Screen Updates
- Replies: 3
- Views: 1336
- Wed Mar 15, 2023 9:05 am
- Forum: 8.2 Stable Release
- Topic: Certain Keyboard Shortcuts - Screen Updates
- Replies: 3
- Views: 1336
Certain Keyboard Shortcuts - Screen Updates
Hi, I'm simplifying my workflow with keyboard shortcuts. I've noticed that certain keyboard shortcuts don't update the screen until you move off the selected task. I use Alt-Right to move the Start Date on 1 day. However if I hit Alt-Right nothing changes on the display until I hit down-arrow to go ...