Gantt Chart shows wrong state when a recurring task is completed
Posted: Tue Oct 20, 2020 1:51 am
If a task is set to reoccur with settings such that the same task will be reused, the result does not display properly. In the recording, step 5 shows that after clicking completion the task is moved to the new start time correctly but is lined out as if it was completed. If an action is taken that causes a refresh, the task will be shown properly as in step 9. It appears the state of the task is ok but it's view is not getting refreshed after the move. The view in step 5 should have looked like in step 9.