[Tips] Pseudo Delay for Gantt View
Posted: Mon Apr 27, 2020 2:57 pm
It seems that it's a little bit tricky to make a delay period between dependent tasks in ToDoList in comparison with GanttProject. Nevertheless I found this trick to be useful for scheduling tasks that shouldn't exceed one day in length - just make a "placeholder task" between two tasks and assign a tag to it, and after that tune your visibility settings to hide that blank task.