Make Week Planner and Calendar respect parent task date calculations
Posted: Sun Jun 25, 2023 2:43 pm
1) The bug is that when you have the option to adjust task's start and due dates based on subtask's earliest of start dates and latest of due dates.
If you have selected a task and then select a time span in a day that is earlier than the earliest of the start days of the rest of it's subtasks and create a new subtask (out of bounds), the bracket in the gannt chart gets updated, which means that the start date of the task got updated but in the weekly planner at top view the time span of the task still shows the initial start date of the task and hasn't changed to include the newly created subtask although it now has a new start date as it proves from gannt chart.
2) And another problem, still with task's start and due dates based on subtask's earliest of start dates and latest of due dates:
In the top area of the Week Planner a parent task with calculated dates based on the subtasks.
The problem is that the parent task can still be moved to the bottom area of the WP, so the duration can be reduced, without any consideration for the calculated dates.
PS: Same in the Calendar. In fact, it seems the settings below (in Preferences > Attribute calculations) are not handled in the Week Planner and Calendar views?
If you have selected a task and then select a time span in a day that is earlier than the earliest of the start days of the rest of it's subtasks and create a new subtask (out of bounds), the bracket in the gannt chart gets updated, which means that the start date of the task got updated but in the weekly planner at top view the time span of the task still shows the initial start date of the task and hasn't changed to include the newly created subtask although it now has a new start date as it proves from gannt chart.
2) And another problem, still with task's start and due dates based on subtask's earliest of start dates and latest of due dates:
In the top area of the Week Planner a parent task with calculated dates based on the subtasks.
The problem is that the parent task can still be moved to the bottom area of the WP, so the duration can be reduced, without any consideration for the calculated dates.
PS: Same in the Calendar. In fact, it seems the settings below (in Preferences > Attribute calculations) are not handled in the Week Planner and Calendar views?