Field "Time Spent" to be calculated from Finish minus Start Topic is solved

How-to's and other software related queries

Moderator: abstr

Post Reply
greg4b
Posts: 11
Joined: Fri Mar 11, 2022 9:52 am

Field "Time Spent" to be calculated from Finish minus Start

Post by greg4b » Thu Apr 04, 2024 9:13 am

Hello,

I was looking for to have the field "Time Spent" to be filled with completed tasks from calculation of "Completed Date / Time" minus "Start Date / Time"

See attachment.

Desireable is the result to be in Days, or working Days etc.
2024-04-04_10-47-26_Notes.png
The closest I found was following post viewtopic.php?f=7&t=1717&p=7659&hilit=s ... late#p7659
But with no realisation.

User avatar
abstr
Site Admin
Posts: 370
Joined: Sun Jul 28, 2019 12:22 pm

Re: Field "Time Spent" to be calculated from Finish minus Start

Post by abstr » Thu Apr 04, 2024 11:53 pm

Hi @greg4b

No, but you could create a custom 'Calculation' attribute (View > Custom Task Attributes...) to do the job.
custtimespent.png
Note: This works in 8.2.7 but has better support in 8.3.RC1

User avatar
abstr
Site Admin
Posts: 370
Joined: Sun Jul 28, 2019 12:22 pm

Re: Field "Time Spent" to be calculated from Finish minus Start

Post by abstr » Wed Apr 10, 2024 8:45 am

Hi @greg4b. I've moved your follow-up request to the Suggestions Forum.

Post Reply