Time Tracker : Add button "Go to task"

Post by kiwibe » Fri May 17, 2024 10:46 am

Hello,

In TDL, I have now 700 "incomplete tasks" and it is the filter I always use.
When I start the Time Tracker, a popup appears.
After that, I go to another task that is not always near the same place.
At this time, the task with the tracker activated is lost. When I would like to go back to this task, I need to scroll with the mouse all over the 700 tasks to find the task with the chronometer icon :
2024-05-17-12-36-54-Window.png
Is it possible de add a button to the popup "Time Tracker" to go back to the task ?
For example :
2024-05-17-12-33-58-Window.png
You have already this behavior in the "Find task" window.
In this window, when we clic on a task, TDL goes directly on the task :
2024-05-17-12-42-45-Window.png
I hope my explanation is clear :-)

Best regards

kiwibe
Posts: 11
Joined: Mon Feb 24, 2020 11:32 am

Re: Time Tracker : Add button "Go to task"

Post by kiwibe » Fri Jun 14, 2024 10:39 am

I am sorry for the images.
Like you asked, it is now uploaded directly to the forum.

User avatar
abstr
Site Admin
Posts: 370
Joined: Sun Jul 28, 2019 12:22 pm

Re: Time Tracker : Add button "Go to task"

Post by abstr » Tue Jun 18, 2024 12:29 am


kiwibe
Posts: 11
Joined: Mon Feb 24, 2020 11:32 am

Re: Time Tracker : Add button "Go to task"

Post by kiwibe » Mon Jul 01, 2024 6:13 am

Great !
Thank you :-)

ConEst
Posts: 14
Joined: Sun Jul 07, 2024 8:02 pm

Re: Time Tracker : Add button "Go to task"

Post by ConEst » Mon Jul 08, 2024 8:43 pm

Hi..
I didn't want to make a new thread for this.
But I had just one question -
Can I keep my Spend Time data intact for main task even after I've deleted sub-tasks under it ?
Is there any option to do that ?

User avatar
abstr
Site Admin
Posts: 370
Joined: Sun Jul 28, 2019 12:22 pm

Re: Time Tracker : Add button "Go to task"

Post by abstr » Mon Jul 08, 2024 11:51 pm

@ConEst

Unfortunately, the time spent shown on the parent is just the subtasks added together and is never actually stored in the parent, so 'no' it's not possible to delete the subtasks and keep the calculated time.

ConEst
Posts: 14
Joined: Sun Jul 07, 2024 8:02 pm

Re: Time Tracker : Add button "Go to task"

Post by ConEst » Tue Jul 09, 2024 6:52 am

Thanks for the prompt reply. :-D