[Gantt Chart] Subtask date handling

How-to's and other software related queries

Moderator: abstr

Post Reply
ispyridis
MVP
MVP
Posts: 100
Joined: Fri Apr 07, 2023 7:05 pm

[Gantt Chart] Subtask date handling

Post by ispyridis » Wed May 29, 2024 6:03 pm

  • download and run
  • accept all suggestions without changing anything
  • just open a brand new session from new download. nothing else.
  • in the example list right click on the last task "getting help"
  • select new subtask under task.
  • check out start date (today) although the parent task was starting a month later
  • open Gannt view and check result. the start date of the parent task has moved to today (at least visually) on the chart.
  • then undo the action while in Gannt chart view. the start date of the parent task will return to the programmed state.
  • then repeat the action from Gannt view do not redo.
  • right click on getting help and select new subtask under task.
  • In Gannt view the new subtask's start date becomes the programmed start date of the parent task, which the most correct behavior because it creates a new subtask within the bounds of the parent thus not changing parent attributes, and letting only the user to do adjust as he wants after first creation, giving full control.
this is happening to previous versions too. and in other views too for example list view. you do not have to alter any settings to get this error just follow the process. check all views

User avatar
abstr
Site Admin
Posts: 370
Joined: Sun Jul 28, 2019 12:22 pm

Re: [Gantt Chart] Subtask date handling

Post by abstr » Sun Jun 30, 2024 2:13 am

You need to clearly state what you think the problem is. I'm not a mind reader.

Please also provide some screenshots.
ispyridis wrote:
Wed May 29, 2024 6:03 pm
check all views
You need to submit reports for all the views that you think are problematic. That's not my job.

I've moved this to the 'Questions' forum until all the required information is supplied.

ispyridis
MVP
MVP
Posts: 100
Joined: Fri Apr 07, 2023 7:05 pm

Re: [Gantt Chart] Subtask date handling

Post by ispyridis » Sun Jun 30, 2024 11:56 am

Ok sorry I did not mention stay on task view or list view they both have the same problem.
So shall i describe the same steps but instead of writing tasks view to write list view ? or calendar view?
You have a global byDesign error

The command creates the new SUBtask TODAY in most views.
If you select a future task and create subtask you reprogram the programmed start date of the parent. when you switch to views like gannt you realize this. Because the visual feedback (the bars) of the Gannt shows the reprogrammed date of the parent and not the initial. The initial as you have said you kept it for your reasons, (this can be seen at the parameters pane). No problem with that. But at least the programmed should be correct it should not start today.

The description im giving about task view is clear.
The same stands at least for list view
Last edited by ispyridis on Sat Jul 13, 2024 6:44 am, edited 1 time in total.

ispyridis
MVP
MVP
Posts: 100
Joined: Fri Apr 07, 2023 7:05 pm

Re: [Gantt Chart] Subtask date handling

Post by ispyridis » Fri Jul 12, 2024 10:20 pm

Your Gannt chart works fine
Please read the titles of the tasks


Also calendar and weekly planner seem ok.
weekly planner needs to update the bar when creating a task outside bounds of parent, like in gannt.

Task view has problem
List view has problem
Evidence board has problem
Kan Ban has problem
Mindmap has a problem
Worload has a problem

all these views when create a new subtask at bottom of task

This is why I say the problem is by conception
You have worked so hard you really got to fix this problem.
"New subtask at bottom of task" is a command that is used very often when plan future events.
ToDoList_PrVh0ixhhq.png
Attachments
sample Introduction.tdl
(66.66 KiB) Downloaded 29 times

User avatar
abstr
Site Admin
Posts: 370
Joined: Sun Jul 28, 2019 12:22 pm

Re: [Gantt Chart] Subtask date handling

Post by abstr » Sat Jul 13, 2024 2:01 am

I'm sure that I already stated that if you want subtasks to be created with their parent dates then you need to make use of the inheritance options in the preferences.

Otherwise, only the date-related views support this by default.

ispyridis
MVP
MVP
Posts: 100
Joined: Fri Apr 07, 2023 7:05 pm

Re: [Gantt Chart] Subtask date handling

Post by ispyridis » Sat Jul 13, 2024 6:46 am

no you haven't mentioned this.
Let me test though if it solves the problem.

ispyridis
MVP
MVP
Posts: 100
Joined: Fri Apr 07, 2023 7:05 pm

Re: [Gantt Chart] Subtask date handling

Post by ispyridis » Sat Jul 13, 2024 7:48 am

fcOdAYnjQz.png
As I thought now you have problem with tasks that are running or have ended but you want to add a new subtask and revive the parent.
In these cases it should create the task today.

You also have another option feature that needs to be coordinated.
Is the option that keeps undefined tasks that have passed in today.
I'll try to see this option how it affects future tasks.

The tasks at the bottom and their subtasks were created in Gannt view.

Apart from these from your previous message you can still see that even without the option you are suggesting, gannt view has different behavior than the rest. it is like the option is checked by default which i prefer to be truthful.

Let me know if you need more help to fix this or if there are settings that i'm missing