Dependenscies Gant chart

Post by rolf_rebmann@web.de » Tue Sep 24, 2024 11:58 am

Hello,
I would like to display dependencies in the Gantt in such a way that there is a certain amount of time between two tasks and the next task does not come directly after the one before it.

Hopefully what I wrote ist understandable.

Regards
Rolf

User avatar
abstr
Site Admin
Posts: 370
Joined: Sun Jul 28, 2019 12:22 pm

Re: Dependenscies Gant chart

Post by abstr » Thu Sep 26, 2024 12:04 am

Hi @rolf_rebmann@web.de

You can do this by specifying a 'Lead In' time in the 'Task Dependencies' dialog
dependsleadin.png