New Task at Top
Creates a new task at the very top of the tasklist.
New Task at Bottom
Creates a new task at the very bottom of the tasklist.
New Task at Top of Selected Task's Parent
Creates a new task which is a sibling to the selected task at the top of their common parent.
New Task at Bottom of Selected Task's Parent
Creates a new task which is a sibling to the selected task at the bottom of their common parent.
New Task Above Selected Task
Creates a new sibling task immediately before the selected task.
New Task Below Selected Task
Creates a new sibling task immediately after the selected task.
New Dependent Task Below Selected Task
Creates a new sibling task immediately after the selected task and makes the newly created task dependent on the previously selected task.
New Subtask at Top of Selected Task
Creates a new sub-task above any other sub-tasks in the selected task.
New Subtask at Bottom of Selected Task
Creates a new sub-task below any other sub-tasks in the selected task.
Split Selected Task into Two (2) Equal Subtasks
Creates two subtasks and allocates half of the time estimate to each.
Note: This operation cannot be performed on a task which already has subtasks Note: If any time has already been spent on the task then this is allocated entirely to the first subtask.
Split Selected Task into 'n' Equal Subtasks
Creates two or more subtasks and splits the time estimate equally between them. (See notes for previous item).